[Nov 08, 2022] Valid C_TS422_2021 Test Answers Full-length Practice Certification Exams
Accurate & Verified 2022 New C_TS422_2021 Answers As Experienced in the Actual Test!
SAP C_TS422_2021 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Lean Manufacturing in SAP S/4HANA 8% - 12% | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. |
| Capacity Planning in SAP S/4HANA 8% - 12% | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. |
| Advanced Planning in SAP S/4HANA > 12% | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts |
| Introduction to SAP S/4HANA Production Planning < 8% | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. |
| Demand Management in SAP S/4HANA < 8% | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. |
| Introduction to SAP S/4HANA Supply Chain Planning < 8% | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. |
| Production Orders in SAP S/4HANA > 12% | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. |
SAP C_TS422_2021 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA Manufacturing consultant profile. This certification proves that the candidate has an overall understanding and in‐depth technical skills to participate as a member of a project team in a mentored role.
NEW QUESTION 10
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Replenishment strategy
- B. Control cycle
- C. Rate routing
- D. Production supply area
Answer: B
NEW QUESTION 11
When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?
- A. The plant-specific status
- B. The most restrictive status
- C. The cross-plant status
- D. The last restrictive status
Answer: B
NEW QUESTION 12
For which categories can you define BOMs in SAP S/4HANA?
- A. Work Center
- B. Document Structure
- C. Class
- D. Sales order
Answer: B,D
NEW QUESTION 13
Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)
- A. Use a resource group.
- B. Use heuristic.
- C. Use a propagation range.
- D. Use a planning group.
Answer: B
NEW QUESTION 14
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?
- A. Run MRP with quota arrangement.
- B. Run MRP with automatic selection of production version.
- C. Run PP/DS heuristics for repetitive manufacturing.
- D. Assign planned orders manual lying the planning table.
Answer: A,C
NEW QUESTION 15
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
- A. Planning with final assembly (40)
- B. Make-to-order production (20)
- C. Planning at assembly level (70)
- D. Planning without final assembly (50)
Answer: D
NEW QUESTION 16
Your quality department detect a deviation in a raw material batch. Unfortunately, this batch has already been used in producion. How can you indentify all affected finish goods stocks?
- A. Use the material staging report.
- B. Use the batch information cockpit.
- C. Use the material where-used report.
- D. Use batch determination.
Answer: B
NEW QUESTION 17
Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing.
What is the impact of this decision?
- A. Net requirement calcualtion is sales-order specific.
- B. A sales-order-specific planning run is required.
- C. Storage location MRP areas are required.
- D. Production orders specific stock is created
Answer: A,B,D
NEW QUESTION 18
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider?
- A. The number of leading zeros for internal numbers is client-specific.
- B. The maximum mater all number length is 40 for external numbers and 18 for internal numbers
- C. The display template for material numbers applies to all clients.
- D. In Customizing you can decide by material type whether to use the long material number.
Answer: B,C
NEW QUESTION 19
Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag?
- A. Material
- B. Work center
- C. Plant
- D. Production version
Answer: A,B
NEW QUESTION 20
How can you set up the supply source for the Kanban process in SAP S/4HANA?
- A. Using purchasing costs for automated source prioritization
- B. Using stock transfer reservations for stock transfer
- C. Using purchase orders for external procurement
- D. Using run schedule quantities for in-house production
- E. Using quotations for internal and external procurement
Answer: B,C,D
NEW QUESTION 21
Which time elements are relevant for lead time scheduling of a production order?
- A. Planned delivery time
- B. Float after production
- C. Total replenishment lead time
- D. Setup time
Answer: A,B
NEW QUESTION 22
What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A. The planed order is converted to production order.
- B. The planed order's component availability is checked.
- C. The planned order's components are copied to the picking list.
- D. The planed order generates capacity requirements
Answer: D
NEW QUESTION 23
In the Capacity Scheduling Table, which settings can you select for the planning strategy? Note: There are 3 correct answers to this question.
- A. Scheduling control
- B. Direction
- C. Finiteness level
- D. Fixed pegging
- E. Planning mode
Answer: A,B,E
NEW QUESTION 24
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?
- A. SAP SuccessFactors
- B. SAP Ariba
- C. SAP Concur
- D. SAP Hybris
- E. SAP Fieldglass
Answer: B,C,E
NEW QUESTION 25
What detremines whatherthe planned independent requirements in MRP are consumed by other requrements?
- A. Requirements type
- B. Order type
- C. Requirements profile
- D. Consumption sequence procedure
Answer: A
NEW QUESTION 26
For a production version to be valid and consistent what requirements must be fulfilled?
- A. The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
- B. The assigned routing must be a rate routing.
- C. The assigned routing must NOT have alternative sequences.
- D. The deletion flag must NOT be set for the bill of materials (BOM) or the routing.
- E. The lot size range must be within the lot-size range of the assigned routing.
Answer: A,D,E
NEW QUESTION 27
When can the automatic material availability check occur in a production order?
- A. At order release
- B. At order creation
- C. At order settlement
- D. At order confirmation
Answer: A,B
NEW QUESTION 28
What does the material type influence?
- A. Which plant specific status is allowed
- B. Which material master views can be maintained
- C. Whether the material is produced in-house, procured externally or bouth
- D. Which document types are allowed
Answer: B,C
NEW QUESTION 29
In the Schedule Production app which setting can you make for the planning strategy?
- A. Fitness level
- B. Scheduling control
- C. Direction
- D. Fixed pegging
- E. Planning mode
Answer: B,C,E
NEW QUESTION 30
During production order creation, several valid production versions are found. How does the system choose the production version?
- A. Valid period or sale order
- B. Lot size or material cost
- C. Planned order or material number
- D. Alphanumeric or quota arrangement
Answer: D
NEW QUESTION 31
How can you achive a feasible production plan in case of capacity constraints?
- A. Execute an infinite production planning run
- B. Form optimum sequence to reduce setup times
- C. Reduce the planning window
- D. Select an alternative mode on a resource.
- E. Adjust the available capacity.
Answer: B,D,E
NEW QUESTION 32
How can you carry out cost object controlling for production orders?
- A. Milestone-related
- B. Cost-related
- C. Order-related
- D. Product-related
Answer: C,D
NEW QUESTION 33
......